Pathway Bridge Decks

Wood decks replaced on 100-year-old bridges along the pathway.

Objectives

  • Improve safety on the pathway bridges.
  • Make bridges more resilient to tidal flows.
  • Maintain the pathway connection between Mill Valley and Sausalito.

Features

  • Safely remove old deck boards without impairing structure of the bridges.
  • Install new redwood decks.
  • Minimal pathway traffic disruption.

Timeline

  • Fall 2019: Planning and installation on first two bridges.
  • Winter 2021: Installation on additional two bridges.